English Woman's Journal - France needs more Canadair water bombers but building them is painfully slow

France needs more Canadair water bombers but building them is painfully slow


France needs more Canadair water bombers but building them is painfully slow
France needs more Canadair water bombers but building them is painfully slow / Photo: Thibaud MORITZ - AFP

As French firefighters struggle to contain the worst wildfires in living memory with just 12 aerial water bombers, production of the iconic aircraft creaks along half a world away in a Canadian factory.

Change text size:

Canadairs are a prime weapon in fighting blazes in rugged, often remote landscapes. But building the specialized aircraft is a time-consuming process, made harder by a nine-year production gap that left the complex supply chain in tatters.

Although manufacturer De Havilland restarted production in 2024, the first delivery -- of just two aircraft -- to France won't happen until at least 2028.

- Rivet-by-rivet -

At a plant in Calgary that AFP visited, the fuselages of the aircraft -- capable of scooping up almost 6,000 liters of water in 12 seconds by gliding along a lake -- were being drilled and riveted by hand.

The relative lack of automation compared to other manufacturers is part of the reason why the factory can only produce 10 planes per year.

"On the fuselage, everything is done manually, so every hole, every rivet you see on the fuselage is being done manually," Operations Director Victor Ocadiz told AFP.

The shortage of aircraft and long wait for more have kicked off a political ruckus in France, with opposition parties accusing the government of hindering firefighting efforts through budget cuts.

But the problems lie at least partly back in Canada.

Previous builder Bombardier halted production in 2015. Production was only restarted after an initial order for 22 planes in 2024 by the European Union, France, Spain, Italy, Greece, Portugal and Croatia, De Havilland Head of Strategy Jean-Philippe Cote said.

Since then, the order book has grown to 40 aircraft, with France ordering two next-generation DHC-515s in 2024 as part of the European order, followed by two more in June.

"We have two aircraft to deliver to France in 2028-2029 ... and the two aircraft announced last month for 2032-2033," Cote said.

A De Havilland spokesperson wouldn't be drawn on the exact month of deliveries, saying only that they were "in line with forecasts."

French Interior Minister Laurent Nunez said in June that the 2028 deliveries would happen in April and November of that year, while stressing that the timetable needed to be "respected."

The first DHC-515 -- the modernized version of the water bomber -- will go to Greece, Cote said, "in early 2028."

- 50,000 parts -

The near-decade gap between Bombardier's assembly lines falling silent and De Havilland starting its own saw supply chains wilt.

The group had to put "more than 50,000" different parts back into production and "select new suppliers because the previous suppliers no longer existed," Cote said.

And while that process meant restarting production took time, it will benefit the 160 older-generation Canadairs still in service around the world -- half of which are in Europe and the other half in North America, with some more than 30 years old.

Thanks to the restart of production, "if an aircraft is damaged, we can quickly take a part from the production line and send it to France. It is becoming increasingly easy for us to meet" repair needs, De Havilland's strategy chief said.

Ch.McDonald--EWJ

Featured

Those who profited from fund scandal 'identified': Turkish minister

Everyone who profited from the sprawling multi-billion dollar investment fund scandal gripping Turkey has been identified, Finance Minister Mehmet Simsek said on Tuesday, expressing confidence the markets would emerge stronger from the controversy.

Indonesian anger builds over wildfires, toxic haze

Indonesians protested in several cities on Tuesday, raging against wildfires and a toxic haze that has made thousands unwell for weeks on end in a crisis that has engulfed Southeast Asia.

Erling Haaland Buys Villa at Abu Dhabi’s Jacob & Co Beachfront Living

Manchester City striker Erling Haaland has purchased a villa in the Jacob & Co Beachfront Living development on Abu Dhabi’s Al Jurf coast.

Polaris Renewable Energy Awards Key Supply Contract and Issues Notice to Proceed on Punta Lima Battery Storage Investment

TORONTO, ON / ACCESS Newswire / October 20, 2026 / Polaris Renewable Energy Inc. (TSX:PIF) ("Polaris" or the "Company") is pleased to announce that it has awarded and executed a contract with Trina Energy Storage Solutions (Singapore) Pte. Ltd. ("Trina Storage") for the supply of battery energy storage systems ("BESS") for the Company's Punta Lima project in Puerto Rico. Trina Storage is a global utility-scale energy storage provider with 30 GWh of BESS projects commissioned and under execution worldwide, including more than 6 GWh across Latin America and the Caribbean.

Change text size: